Notification to StarHub Cable Vision Ltd of Commencement and Performance of Earthworks
- Definition
1.1 Telecommunication Cables
All coaxial cables. - Administration Procedure
2.1 The principals/contractors must purchase the latest plant information from
StarHub Cable Vision Ltd for the area of intended earthworks.
2.2 The contractors must engage licensed TCDW to locate and trace the plant
routes before commencement of any earthworks in the vicinity of
telecommunication cables.
2.3 The TCDW must submit the detected plant route information to contractors and
service provider and keep a set of records for future reference.
2.4 Upon receipt of notification, StarHub Cable Vision would response within 7
days, from the time of receipt, with an acknowledgement of notification or
response with a need of site visits with principals/contractors for further
discussions and consultations.
2.5 Contractors could proceed with the earthworks on the scheduled commencement
dates upon receipt of StarHub Cable Vision 's reply that such earthworks are
permitted.
2.6 Each notification will expire within a month from the date of notification
if the intended earthworks are not carried out. Upon expiry, a fresh
notification is required from the contractor again to notify StarHub Cable
Vision on the new scheduled commencement date. - Submissions And Conditions
3.1 Notice shall be submitted using the Notice of Commencement of Earthworks
form
3.2 Application shall be sent by post or submitted by hand to StarHub Cable
Vision Ltd.
3.3 Charges to process notice will be $20 each. For consultation work including
site inspection, call-outs for cable cuts and other field work required, charges
will be $60 for half day or less than 4 hours and $100 for one full day.
3.4 All documents to accompany Notices e.g. cable detection drawings by licensed
TCDW, proposed site plan and work schedule.
3.5 Conditions and safety measures, if necessary, will be conveyed at the same
time in StarHub Cable Vision's response.
3.6 StarHub Cable Vision reserves the right to add on to given conditions during
the duration of earthworks if damage to cable is imminent. - Method Of Payment
4.1 Payment is to be made by cheque and payable to "StarHub Ltd".